The commissioning of the multi-drum filter
The Patpre2000 multi-drum · Part 5
After dressing the filter, this last part of the report presents its installation, the setting up of brushes and ventilation, as well as the first connections to the pond.
Prepare the location and carry the filter
It remains to prepare the location at the back of the barbecue.
Transport is not simple: the whole must weigh nearly 100 kg. In this realization, three people were required to move it.
The filter has almost arrived at its destination; it remains to be put in place.
The filter is now installed at its location.
Purges and brush supports
Backwash outlets still need to be connected.
To keep the brushes in place and facilitate their cleaning, the author installs them on a flexible electrical tube. Clips hold them and a sleeve closes the tube.
Brushes and aeration of biological zones
Here is the result with two rows of brushes in place.
This view shows the two bubblers placed under the grids of biological zones, in tanks 2, 3 and 4.
The start of traffic
The pump is connected and the water arrives. The T-connector fulfils its role: the author indicates that if the pump stops, the circuit defuses. The two clips that hold each brush on the hose are also visible.
This is the exit of the can containing the brushes.
The return to the pond
An overview of the installation.
This test shows the connection of the outlet to the pond. The vertical pipe must be longer. The junction with the existing pipe is made using a 90 to 110 mm connection.
Water arrival to be completed
In this photo, the second entrance is still open. It must be closed if it is not used: if the level rises, the water could come out by this opening.
The remaining finishes to be achieved
At this stage of the report, the author still plans several finishing works and plans to present them on another page:
- Fill the space between the cans with "chips" of packaging to strengthen insulation.
- Fix the top panel after ensuring that there are no leaks, then make the seal between this panel and the four tanks.
- Install electricity, air pumps and UV.
- Reunite the back-washing purges.
- Make a lid.
A production of Patpre2000 for Aquatechnobel.